Workplan for AVO Demo 2005

No. Milestone Host Date Tasks
M1 SWG meeting CDS 21-Jun-04 T1.1
M2 science selection meeting CDS 21-Jul-04 T1.2
M3 Astrogrid middleware assessment ESO 12-Aug-04 T3.1
M4 application and data provider meeting CDS 14-Oct-04 T1.3/4, T4.1
M5 component review meeting IoA 17-Nov-04 T2.1-4, T3.2-5, T4.2/3, T5.1-3
M6 internal release and readiness review ESAC 9-Dec-04 T3.6, T4.4
M7 code freeze, readiness review, dry-run ESO 17-Jan-05 code freeze
M8 demo trial meeting ESAC 24-Jan-05 T1.5, T6.1-3
M9 demo event ESAC 25+26-Jan-05 T1.6 (all)


No. Scope of Task Supervision
T1 science cases PaoloPadovani, ST-ECF
T1.1   collect SWG feedback and input   done
T1.2   definition and selection   done
T1.3   data collections and providers   science team
T1.4   detailed design   science team
T1.5   execution, produce sci. results   science team
T1.6   presentation, dissemination   AVO Exec
T2 SED generation MarkusDolensky, ESO
T2.1   data curation   Anita Richards
T2.2   special workflow operators   Mark Allen
T2.3   visualization + analysis   Anita Richards
T2.4   SED support library   Markus Dolensky/Pedro Osuna
T3 data center infrastructure KeithNoddle, Astrogrid
T3.1   identify useful middleware components   done
T3.2   workflow builder   Paul Harrison
T3.3   workflow execution and monitoring   Paul Harrison
T3.4   shared storage   Martin Hill
T3.5   data access layer   Martin Hill
T3.6   master registry   Kevin Benson
T4 integration KeithNoddle, Astrogrid
T4.1   IVOA compliance   Markus Dolensky
T4.2   external applications   Nicholas Walton
T4.3   shared storage browser   Pierre Fernique/Dave Morris
T4.4   population of registry   Kevin Benson/Sebastien Derriere
T5 AVO prototype FrancoiseGenova, CDS
T5.1   improvements   Francois Bonnarel
T5.2   extensions   Sebastien Derriere
T6 demo event ChristopheArviset, ESA
T6.1   local organization   Christophe Arviset
T6.2   technical setup   Fernando Felix
T6.3   definition of agenda   science team


Task Descriptions

T1 science cases

Responsible: PaoloPadovani, ST-ECF

T1.1 collect SWG feedback and input

Interact with SWG sub-groups to get feedback on previous demos and new scientific needs: summary.

T1.2 definition and selection

Collect ideas for scientific cases and define scenarios together with SWG.

Two scientific scenarios have been selected:

T1.3 data collections and providers

Identify required data sets and their providers.

T1.4 detailed design

Flow charts incl. required input, manipulations, conversion, desired output.

T1.5 execution, produce sci. results

Walkthroughs for both scenarios; execute walkthroughs; capture scientific results.

T1.6 presentation, dissemination

Implementation, discussion, review thereof at demo trial meeting M7.

T2 SED generation

Responsible: MarkusDolensky, ESO

T2.1 data curation

Make data sources accessible; liaise with data providers; implement new access services where applicable; ingest catalogs into Vizier where applicable.

T2.2 special workflow operators

Identify, design and implement operators on SED objects which will either become part of workflows or the AVO prototype's filter functionality.

T2.3 visualization + analysis

Identify requirements of SED user front end; features for analysis and visualization; supervise implementation and testing.

T2.4 SED support library

Work with STScI (Ivo Busko) on a SSA support library for reading and writing spectral data.

AndreSchaaff released SAVOT V2.5 which supports VOTable 1.1, a pre-requisite for manipulating data compliant to an SSA data model.

T3 data center infrastructure

Responsible: KeithNoddle, Astrogrid

T3.1 identify useful middleware components

PAL (SkyNode), MySpace, JES/CEA (workflow); further details below.

T3.2 workflow builder

Tool for building workflows; there will be a GUI which talks to the master registry in Leicester (T3.6).

T3.3 workflow execution and monitoring

Deployment of Job Execution System (JES), deployment of Common Execution Architecture (CEA).

Selecting, triggering and monitoring of workflows is part of the Astrogrid Web Portal and will be re-used in this context.

T3.4 shared storage

MySpace; deployment of file stores and the MySpace controller (server) component.

T3.5 data access layer

Adaptation and deployment of the Publisher's Astrogrid Library (PAL). This includes adapters for ADQL (SkyNodes) and SIA services.

T3.6 master registry

A full registry; AVO partners and data providers will register services and data collections against a registry in Leicester. The registry will harvest at least from Vizier as well as one full NVO registry.

Test system: registry index (Hydra server in Leicester).

T4 integration

Responsible: KeithNoddle, Astrogrid

T4.1 IVOA compliance

Identify minimal standards required for the AVO demo 05; guide data providers and tool builders as which specifications to develop against: http://www.euro-vo.org/internal/Avo/DemoPlan05on20040812/ivostds4avodemo05.pdf

T4.2 application servers

Identify and supervise integration of external applications into workflows. Acquire test data and liaise with application experts and relevant providers as needed.

T4.3 shared storage browser

Integrate a MySpace browser into the AVO prototype load dialog. It'll allow access to workflow input/output data put on distributed file stores.

T4.4 population of registry

Help data and service providers to populate the master registry. Establish functional OAI interfaces to a NVO registry and CDS (Vizier) registry. Provide stable service for demoing.

T5 AVO prototype

Responsible: Main.FrançoiseGenova, CDS

T5.1 improvements

Improvements as described here.

T5.2 extensions

Extensions as described here.

Note: Plug-ins are singled out as separate tasks and some extensions fall under external applications.

T6 demo event

Responsible: ChristopheArviset, ESA

T6.1 local organization

Form LOC; manage logistics of meeting.

T6.2 technical setup

Specify system requirements and H/W needs for demo; provide equipment for M8 and M9:
  • for details see Annex 2 of the telecon minutes from Oct 21st.

T6.3 definition of agenda

Form POC, define agenda, planning.



# Edit menu  


Topic revision r1.44 - 19 Jan 2005 - 17:12 - MarcoLeoni
Topic parents: WebHome > WorkAreas > WorkAreaOne > AvoDemo2005
Copyright © 2003 by the contributing authors. All material on this collaboration tool is the property of the contributing authors. Ideas, requests, problems regarding AVO TWiki ? Send feedback.
Avo.WorkPlanDemo05 moved from Test.WorkPlanDemo05 on 14 Sep 2004 - 09:32 by MarkusDolensky - put it back